How to Reduce the Number of MRO Suppliers: A 4-Step Plan

By the IndustryMRO Team  •  6 min read  •  Published October 2026

Almost no plant plans to have forty MRO vendors. The list grows one urgent purchase at a time. A machine stops, someone calls a new vendor who can deliver today, and that vendor stays on the list long after the breakdown is forgotten. A few years later, nobody is sure who supplies what, prices differ from one order to the next, and every delivery needs a follow-up call. This guide shows how to reduce the number of MRO suppliers in four practical steps: group your spend by category, choose one primary supplier for each, keep one backup, and review every six months. It is written for maintenance and procurement teams in Indian plants, and it is built around one idea: buying that is planned, not panicked.

Why Too Many MRO Suppliers Becomes a Problem

MRO purchases are usually small in value but large in number. Each extra supplier adds to the daily workload and the risk:

  • More paperwork for small orders: more quotes, purchase orders, invoices and payment follow-ups for the same total spend.
  • Uneven prices: the same bearing or fastener is bought at different rates from different vendors, and nobody has the full picture.
  • Delivery chasing: when a vendor only sees you occasionally, your order is rarely a priority, so dates slip and someone has to call.
  • Emergency vendors who never leave: suppliers added in a rush stay on the list without ever being reviewed.

A look at the numbers (UK data): the 2025 Indirect Procurement Report by RS and the Chartered Institute of Procurement & Supply (CIPS) found that UK organisations used an average of 92 MRO suppliers, and that about half of procurement professionals planned to consolidate their supplier base. This is UK data, not Indian, but the pattern of supplier sprawl will look familiar to many plants here.

The 4-Step Plan at a Glance

1
Group your MRO spend by category

See how many vendors you use for bearings, fasteners, electricals and the rest.

2
Choose one primary supplier per category

Decide on delivery reliability and consistent pricing, not on the lowest quote alone.

3
Keep one backup supplier

Especially for parts that can stop a line.

4
Review every six months

Check delivery, price and quality, then adjust the list.

Step 1: Group Your MRO Spend by Category

You cannot reduce what you have not counted. Take the last 12 months of purchase orders or invoices from your accounts system or Excel sheet, and sort them into categories. A simple split works for most plants: bearings, fasteners, electricals, cables, PPE, lubricants, hand tools and consumables. If you need a starting point, our MRO items list groups common items by category.

For each category, note three things: how many vendors you bought from, how many orders you placed, and the total spend. Here is what the result can look like (illustrative numbers only):

CategoryVendors usedOrders in 12 monthsSpend
Bearings648₹3.2 lakh
Fasteners971₹1.8 lakh
Electricals740₹4.5 lakh
PPE422₹0.9 lakh
Lubricants315₹1.4 lakh

The categories with the most vendors and the most small orders are usually where consolidation helps first. In this example, fasteners stand out: nine vendors for a modest spend.

Start small. Do not try to fix every category at once. Pick the one with the most vendors, run the whole plan on it, and learn what works before moving on.

Step 2: Choose One Primary Supplier per Category

The primary supplier is the one you go to first for that category. Choose on more than price. Look at:

  • Delivery reliability: will they confirm the delivery date in writing, and keep it?
  • Price consistency: are their rates steady, and are they competitive when you compare quotes side by side?
  • Range: can they supply most of the items you buy in that category, so you are not splitting orders?
  • Response time: how quickly do they reply to a quote or a breakdown call?
  • Documents: correct invoices, and test certificates where the item needs them.

To compare vendors fairly, ask them to quote against the same specification. A clear RFQ for MRO items keeps quotes comparable, and a comparative statement puts price, GST, freight, delivery time and payment terms in one table. The cheapest quote is not always the cheapest purchase once a late delivery stops a machine.

Step 3: Keep One Backup Supplier

Reducing suppliers does not mean relying on a single one. For every category, keep one approved backup. This matters most for parts that can stop a line, such as the bearing on a key motor or a specific contactor. The backup is what protects you on the day the primary supplier cannot deliver.

Keep the backup warm. Give them a small share of regular orders so they know your specifications and your team knows theirs. A backup you have never ordered from is a stranger when you need them most.

Step 4: Review Every Six Months

A supplier list is not a one-time project. Every six months, look at how each primary and backup supplier performed. A simple scorecard is enough:

CheckWhat to look at
On-time deliveryDelivery date against the date confirmed in writing
PriceChange since the last review, and against other quotes
QualityRejections, returns and wrong items
ResponseTime taken to reply to a quote or an urgent call
PaperworkCorrect invoices and certificates, without chasing

If a primary supplier keeps missing dates, promote the backup and bring in a new backup. If a supplier does well, say so, and consider giving them more of the category.

Common Mistakes to Avoid

  • Cutting to one supplier overnight. One vendor for everything is a single point of failure.
  • Choosing on price alone. A low quote with an unreliable delivery date costs more in downtime than it saves.
  • Moving every category at once. You will overload your team and miss problems.
  • Not telling the maintenance team. If maintenance keeps calling the old vendor directly, the list will grow back. Share the approved suppliers with everyone who places or requests orders.
  • Dropping good specialist vendors. Consolidation is about removing duplicates and one-off emergency vendors, not about cutting a reliable supplier of a hard-to-find item.

What About Emergency Purchases?

Even with fewer suppliers, breakdowns happen. The difference is how ready you are. With a primary and a backup for each category, you already know who to call, what they can supply and how fast they respond. A short list of critical spares, kept in stock or on a pre-agreed order, reduces the number of panic calls. That is the real goal of the whole plan: industrial buying that is planned, not panicked.

Frequently Asked Questions

How many MRO suppliers should a plant have?

There is no fixed number. It depends on the size of the plant, the number of categories and the number of sites. A better target is one primary and one backup supplier for each major category, with a few specialists for hard-to-find items.

Will fewer suppliers cost more?

Not necessarily. Buying more from fewer vendors can give you better pricing and means less time spent on quotes, orders and follow-ups. Prices should still be compared at each review, so that a primary supplier does not become comfortable.

What if my primary supplier fails to deliver?

This is why you keep a backup. Ask for delivery dates in writing, track them, and switch to the backup if dates are missed repeatedly. Review at six months and replace suppliers that do not improve.

Where do I start?

Start with a spreadsheet of the last 12 months of purchases, grouped by category. Pick the category with the most vendors and run the four steps on that one first.

Should I remove small local vendors from the list?

Not automatically. Keep any vendor who is reliable and supplies something you cannot easily get elsewhere. The aim is to remove duplicate and one-time emergency vendors, not good suppliers.

Want fewer vendors and fewer last-minute calls?

Send us your requirement for one category and we will share a quote with the delivery date confirmed in writing before you order. Industrial buying should be planned, not panicked.

Send Us Your Requirement

For the wider picture, read our guide on what MRO procurement is.